Update: 28.07.2026
Liquidated Damages: New Approaches under the Law on Construction 2025
The Law on Construction 2025 formally recognizes liquidated damages as an independent contractual remedy alongside contractual penalties and compensation for actual damages. The reform strengthens contractual predictability while requiring parties to distinguish carefully between compensatory and punitive remedies.
Liquidated damages are widely used in international contractual practice as a mechanism for allocating risks and improving predictability in contract performance.
Under this mechanism, the parties agree in advance on an amount payable if a specified contractual breach occurs.
Vietnamese law historically did not expressly recognize liquidated damages, leading to uncertainty regarding the validity and enforceability of such clauses.
The Law on Construction 2025 marks a significant development by formally recognizing liquidated damages as an independent remedy, alongside penalties for breach and compensation for actual damages.
Section 1
Legal Framework on Liquidated Damages
1.1. Origin of Liquidated Damages
Liquidated damages originated and developed within the Common Law legal tradition, particularly in England and the United States.
Unlike punitive remedies, liquidated damages are intended to compensate for losses anticipated to arise from a contractual breach, especially where actual losses may be difficult to assess or prove.
Parties may agree in advance on a sum payable as damages, provided that the amount is reasonable and proportionate to the foreseeable loss at the time of contract formation.
Liquidated damages have subsequently been recognized in international contractual practice and commercial instruments, including the United Nations Convention on Contracts for the International Sale of Goods.
1.2. New Regulations under Vietnamese Construction Law
Clause 1, Article 86 of the Law on Construction 2025 provides that bonuses, contractual penalties and compensation for damages must be agreed upon by the parties in the construction contract.
Clause 2 provides that compensation may be determined based on:
The Law on Construction 2025 therefore formally recognizes liquidated damages as a permissible contractual remedy.
Section 2
Civil Law Approach and Practical Application
2.1. The Law on Construction and the Civil Code 2015
Under the Law on Construction 2025, liquidated damages are recognized as an independent remedy, separate from contractual penalties and compensation for actual damages.
Article 360 of the Civil Code 2015 provides that where damage is caused by a breach of obligation, the obligor must compensate for the entire damage unless otherwise agreed by the parties or otherwise provided by law.
Article 419 additionally allows the aggrieved party to claim:
Compensation for actual damages in Vietnamese practice generally requires proof of:
2.2. Distinction between the Available Remedies
Liquidated Damages
A pre-agreed amount intended to compensate anticipated losses, generally without requiring proof of actual loss.
Actual Damages
Compensation determined after the breach based on proven losses and causation.
Contractual Penalties
A remedy intended primarily to deter or sanction breach rather than compensate anticipated loss.
A clause may be labeled as liquidated damages but operate in substance as a penalty if it is designed primarily to deter or punish a breach.
2.3. Potential Impact on Judicial Approaches
Vietnamese judicial practice has historically lacked consistency in its treatment of liquidated damages.
Judgment No. 660/2022/KDTM-PT dated 10 November 2022 of the Ho Chi Minh City People’s Court adopted a progressive approach in a construction contract dispute.
The Court nevertheless confirmed that an amount may be adjusted where it is manifestly excessive in comparison with the actual damage.
2.4. Drafting Liquidated Damages Clauses
Breaches suitable for liquidated damages
Breaches generally unsuitable for liquidated damages
Section 3
Conclusion and Recommendations
The recognition of liquidated damages reflects a broader shift toward greater predictability in contractual risk allocation and closer alignment with international construction practice.
Further implementing regulations should clarify:
Parties should draft liquidated damages clauses specifically and transparently, linking them to obligations where losses are foreseeable and quantifiable.
Regardless of whether damages are pre-determined or based on actual loss, the aggrieved party remains responsible for taking reasonable steps to mitigate its damages.
Reference: Judgment No. 660/2022/KDTM-PT dated 10 November 2022 of the Ho Chi Minh City People’s Court concerning a construction contract dispute.
